how to install sanitary ball valve steps
Jul 29, 2024| Sanitary ball valve opening and closing parts (ball) driven by the valve stem, and around the axis of the valve stem for rotary valves. Mainly used to cut off or connect the medium in the pipeline, can also be used for fluid regulation and control. So do you know how to install sanitary ball valve steps?
Installation of sanitary ball valve steps are as follows:
1, you need to remove the flange end of the two sides of the protective cover, and then in the sanitary ball valve valve body open for flushing and cleaning.
2, the installation must be in accordance with the prescribed signal for the whole machine test, qualified before the installation on the line.
3, in preparation for the revolution pipeline connection, have to first flush and remove the impurities remaining in the pipeline.
4, in the installation period, do not use the actuator part of the ball valve as a lifting lifting point, in order to prevent damage to the actuator and accessories.
5, sanitary ball valves of this type of valve should be installed in the horizontal or vertical direction of the pipeline.
6,After connecting with the pipeline, the specified torque can be used to cross-lock the flange and connecting bolts.
7, stainless steel ball valve installation point near the pipeline can not have a low hanging or the phenomenon of external forces, you can use pipe supports or supports to remove the pipeline deviation.